Development of a schedule-workspace interference management system simultaneously considering the overlap level of parallel schedules and workspaces

Authors
Moon, HyounSeokKim, HyeonSeungKim, ChangHakKang, LeenSeok
Issue Date
Apr-2014
Publisher
ELSEVIER SCIENCE BV
Keywords
Schedule overlap; Workspace interference; Schedule-space conflict impact factor; Location-constraint genetic algorithm; 4D CAD; BIM (building information modeling)
Citation
AUTOMATION IN CONSTRUCTION, v.39, pp 93 - 105
Pages
13
Indexed
SCIE
SCOPUS
Journal Title
AUTOMATION IN CONSTRUCTION
Volume
39
Start Page
93
End Page
105
URI
https://scholarworks.gnu.ac.kr/handle/sw.gnu/19065
DOI
10.1016/j.autcon.2013.06.001
ISSN
0926-5805
1872-7891
Abstract
Schedule-workspace interference is generated when workspaces that share parallel schedules and are physically adjacent to one another exist simultaneously. When workspace interference is generated, securing work performance safety is difficult and constructability can deteriorate due to increased collision risk between resources. The objective of this study is to realize an active simulation system based on building information modeling (BIM) after constructing a genetic algorithm (GA) process for an alternative schedule that minimizes the simultaneous interference level of the schedule-workspace. To accomplish this task, the impact factor of workspace interference, which simultaneously considers schedule overlap and adjacency, was analyzed. From the impact factor, an optimized algorithm based on a location-constraint GA that can minimize workspace interference is suggested. The GA visually simulates the optimization level of the execution schedule compared to the initial plan through interlock with four-dimensional (4D) computer-aided design (CAD). A 4D CAD system that can analyze workspace interference by a GA was developed, and for the developed algorithm and system, a case verification was attempted for a railroad construction project. The results show how a simple visualization-oriented BIM system can be extended to an active schedule management system equipped with decision-making functions of workspace analysis. (C) 2013 Elsevier B.V. All rights reserved.
Files in This Item
There are no files associated with this item.
Appears in
Collections
공과대학 > Department of Civil Engineering > Journal Articles

qrcode

Items in ScholarWorks are protected by copyright, with all rights reserved, unless otherwise indicated.

Related Researcher

Researcher Kang, Leen Seok photo

Kang, Leen Seok
공과대학 (토목공학과)
Read more

Altmetrics

Total Views & Downloads

BROWSE