Managing construction schedule by telepresence: Integration of site video feed with an active nD CAD simulation

Authors
Kang, Leen SeokKim, Hyeon SeungMoon, Hyoun SeokKim, Sung-Keun
Issue Date
Aug-2016
Publisher
ELSEVIER SCIENCE BV
Keywords
Telepresence; nD CAD; Webcam; BIM; Decision making
Citation
AUTOMATION IN CONSTRUCTION, v.68, pp 32 - 43
Pages
12
Indexed
SCIE
SCOPUS
Journal Title
AUTOMATION IN CONSTRUCTION
Volume
68
Start Page
32
End Page
43
URI
https://scholarworks.gnu.ac.kr/handle/sw.gnu/15348
DOI
10.1016/j.autcon.2016.04.003
ISSN
0926-5805
1872-7891
Abstract
In recent years, the increased utilization of building information modeling (BIM) has brought attention to the need for BIM-based operation systems that provide a decision-making feature in addition to visual information: This study constructed a project schedule management system that integrates the data points of an nD computer aided design (CAD) object (e.g., schedule and resource information) with a telepresence concept video management operation system. A methodology was developed that allows the user to monitor the current construction status relative to the design and verify the completion of the facility through real-time comparison between the planned process represented by the nD object and the actual image of the construction site sent from an on-site webcam. An active nD CAD system was developed that possesses features such as a comparative simulation between the on-site image and a 4D object to minimize interference between processes and a 5D object that is specialized to the resource mobilization level of the field. A telepresence-based nD CAD system was developed based on this methodology, and the practicality of the system was verified by webcams installed on a bridge construction site. Thus, the project manager is not only able to utilize the nD object for visualization but is also able to use the system as a decision-making system to formulate the most appropriate project schedule by comparing the nD object with the actual on-site image. (C) 2016 Elsevier B.V. All rights reserved.
Files in This Item
There are no files associated with this item.
Appears in
Collections
공과대학 > Department of Civil Engineering > Journal Articles

qrcode

Items in ScholarWorks are protected by copyright, with all rights reserved, unless otherwise indicated.

Altmetrics

Total Views & Downloads

BROWSE